Full Planning Permission National for Formation of Onshore Landfall Point, Laying of Underground Cable and Erection of Substation at Land from North of Peterhead to South of New Deer, Green Volt Offshore Windfarm (APP-2023-1454)
February 13, 2024 Unknown View on council websiteFull council record
Content
The Committee agreed to defer consideration of
the application, pending further information in relation to:
1) Layout, siting and design
2) Photomontages to
show screening
3) Distances to
neighbouring properties as the distances were variable on the
existing montages
4) The impact on rural
roads
5) Lighting
6) Biodiversity
7) Consultation with
local communities, in particular the Fyvie, Rothienorman and Monquhitter Community Council
Supporting Documents
Details
| Outcome | Defer |
| Decision date | 13 Feb 2024 |