ADforRD/034/24-25 Connaught Studio Roof Contract Variation

October 18, 2024 Assistant Director Regenerative Development (CLT) (Officer) Key decision Approved View on council website
Full council record
Content

To authorise expenditure up to the full budget
of £280,000 for the Connaught Studio Roof Recovering project
if it is found to be necessary. This is in addition to the
expenditure of the Contract Sum committed to Kingsley Roofing of
£210,408.27.

Details

OutcomeRecommendations Approved
Decision date18 Oct 2024
Subject to call-inYes