A/HOU/004/26-27 - Pre Construction Services Agreement for Daniel Close and Gravelly Crescent
November 9, 2026 Deputy CEO & Corporate Director for Housing & Communities (Officer) Key decision Approved View on council websiteFull council record
Decision
Approve the Pre Construction Services Agreement (PCSA) with J Cheesmur & Sons Limited to deliver a suite of work to identify the required costs for tendering the main design and build contract and to de-risk the project. The costs of this are no more than £250,000.00 and the delivery of this work will begin in November 2026 with a 12 week delivery programme.
The works include (but are not limited to):
- Site clearance including vegetation and rubbish removal
- Reconnecting welfare facilities and site set-up
- Investigations into the existing buildings which may include intrusive investigations
- Obtaining updated utilities quotes
- Carrying out remaining design development
- Discharging remaining Planning Conditions
- Developing a programme and fixed price to complete the remaining works
- Resident liaison
Reasons for the decision
The PCSA will enable the Council to progress the stalled developments at Daniel Close and Gravelly Crescent and establish the full scope and cost of the outstanding works required to deliver the 16 affordable homes.
The two-stage approach will help manage project risks, improve cost certainty and ensure value for money. J Cheesmur & Sons Limited was identified as the most advantageous bidder through a competitive tender process, achieving the highest overall score. The PCSA provides a necessary step towards restarting the developments without committing the Council to the full construction contract at this stage.
Alternative options considered
Proceeding directly to a full construction contract was considered but rejected due to uncertainties around site conditions, outstanding works and utility costs, which could expose the Council to additional financial risks through provisional sums.
Not progressing the developments would result in further delays to the delivery of the 16 affordable homes.
The PCSA approach is therefore considered the most appropriate option, allowing the Council to establish costs and manage risks before making a decision on the main construction contract.