Capital Programme Performance Year Ended 31 March 2025 (Cab.11.06.2025/8)
June 11, 2025 Approved View on council websiteFull council record
Decision
RESOLVED
that Cabinet:-
(i)
Note the final financial position on the 24/25
Capital Programme;
(ii)
Approve scheme slippage totalling £30.5M
(paragraph 2.6 and Appendix B refer);
(iii)
Approve scheme re-phasing totalling £0.7M
(paragraph 2.7 and Appendix B refer);
(iv)
Note the total net decrease in scheme costs in 24/25
of £4.5M (paragraph 2.8 and Appendix B refer); and
(v)
Receive an updated 25/26 indicative Capital
Programme position (as part of the Quarterly Finance Monitoring
update).