Capital Programme Performance Year End 31 March 2024 (Cab.11.6.2024/11)
June 11, 2024 Approved View on council websiteFull council record
Decision
RESOLVED
that Cabinet:-
1.
Note the final financial position on the 2023/24
Capital Programme; and
2.
Approve scheme slippage totalling £21.2M
(paragraph 2.6 and Appendix B refer); and
3.
Approve scheme re-phasing totalling £2.3M
(paragraph 2.7 and Appendix B refer); and
4.
Note the total net decrease in scheme costs in
2023/24 of £0.6M (paragraph 2.8 and Appendix B refer);
and
5.
Receive an updated 2024/25 indicative Capital
Programme position (as part of the Quarterly Finance Monitoring
update).
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Jun 2024 |
| Subject to call-in | Yes |