Quarter 2 Capital Monitoring Report as at 30 September 2024
December 10, 2024 Cabinet (Cabinet collective) Approved View on council websiteFull council record
Purpose
Quarterly update on spend against the capital
programme.
Decision
Note:
1)
The forecast capital expenditure for 2024/25 of £28.882M
which is £6.859M lower than the latest agreed capital
programme budget of £35.741M;
2)
The 2024/25 significant forecast outturn variations and
explanations for them as shown in section 4;
3)
The quarter two forecasts and impact of scheme variances for
2024/25 on future years’ capital expenditure;
4)
The latest forecast of capital receipts, grants and contributions
for 2024/25 in section 5;
5)
The risks associated with the capital forecasts are as detailed in
section 11;
6)
The latest approved capital programme for 2024/25 to 2027/28 and
the financing as shown in section 6 and
detailed in Appendix 1; and
7)
The capital programme remains fully funded from the council’s
own resources up to 2027/28, based on the latest forecast of
available resources.
Request Council to approve the following
capital programme amendments as set out in paragraphs 1.7 and
1.8:
8)
A budget virement of £5.365M from the Manydown Land and Infrastructure Funding Scheme to
the Manydown Development scheme
(2024/25 £2.365M and 2025/26 £3.000M).
9)
The renaming and repurposing of The Malls Upgrading/Updating scheme
to Town Centre Improvements.
Related Meeting
Cabinet - Tuesday, 10th December, 2024 6.30 pm on December 10, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Dec 2024 |