Quarter 1 Capital Monitoring Report as at 30 June 2025
October 7, 2025 Cabinet, Council (Other) Approved View on council websiteFull council record
Purpose
Quarterly update on spend against the capital
programme.
Decision
Cabinet note:
1.
The forecast capital expenditure for 2025/26 of £19.514M
which is £0.688M lower that the latest agreed capital
programme budget of £20.202M;
2.
The approved increases to the 2025/26 capital budget from S106
contributions and scheme rephasing under the Chief Finance
Officer’s delegated powers as shown in section 2 of the
report;
3.
The 2025/26 significant forecast variations and explanations for
them as
shown in section 3
of the report;
4.
The latest forecast of capital receipts, grants and contributions
for 2025/26 in section 4 of the report;
5.
The risks associated with the capital forecasts are as detailed in
section 9 of the report;
6.
The latest approved capital programme for 2025/26 to 2028/29 and
the financing as shown in section 5 and detailed in Appendix 1 of
the report; and
7.
The capital programme remains fully funded from the council’s
own resources up to 2028/29, based on the latest forecast of
available resources.
Cabinet recommend Council to approve:
8. Changes to the capital programme as described in
section 6 of the report to support the delivery of Council Plan
Priorities as follows:
·
an increase to the Manydown Development
scheme of £1.139M in 2025/26 and £0.153M in
2026/27;
·
a reduction to the New Waste Collection Contract scheme of
£0.384M in 2025/26 and £0.069M in 2026/27;
·
an increase to the Local Authority Housing Fund scheme of
£0.644M in 2025/26; and
·
a new capital scheme for Affordable Housing Schemes with a capital
budget of £0.301M in 2025/26.