Quarter 3 Capital Monitoring Report as at 31 December 2025

March 10, 2026 Cabinet (Cabinet collective) Unknown View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...noted the Quarter 3 Capital Monitoring Report as at 31 December 2025, which provided an update on performance against the approved capital programme and confirmed the programme remains fully funded.

Full council record

Purpose

Update report on performance against the
approved capital programme for the quarter.

Decision

Cabinet note:
 
1)        
The latest forecast capital expenditure for 2025/26 is
£17.366M as reported to and approved by Council on 26
February 2026 in the Capital Programme Update and Strategy Report
2025/26 to 2029/30.

 
2)        
The 2025/26 significant forecast variations and explanations for
them have previously been reported in the report to Council;
 
3)        
The latest forecast of capital receipts, grants and contributions
for 2025/26 in section 3 of the report;
 
4)        
The risks associated with the capital forecasts are as detailed in
section 6 of the report;
 
5)        
The latest approved capital programme for 2025/26 to 2029/30 as
shown in Appendix 1 of the report; and
 
6)        
The capital programme remains fully funded from the council’s
own resources up to 2029/30, based on the latest forecast of
available resources

Related Meeting

Cabinet - Tuesday, 10th March, 2026 6.30 pm on March 10, 2026

Supporting Documents

Report.pdf

Details

OutcomeInformation Only