Local Electric Vehicle Infrastructure (LEVI) - Inter Authority Agreement (WL)

October 1, 2026 Cabinet Member for Sustainable Transport Strategy (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cabinet Member for Sustainable Transport Strategy approved the Local Electric Vehicle Infrastructure (LEVI) Inter-Authority Agreement on 01/10/2026. The decision delegated approval to the Executive Director of Sustainable Communities to sign the agreement on behalf of Bath and North East Somerset Council. This agreement formalises the council's role in implementing the LEVI project and delivering charging infrastructure.

Full council record

Purpose

The West of England Mayoral Combined Authority (MCA) has been awarded £4.2m of Local Electric Vehicle Infrastructure (LEVI) funding to support the delivery of public electric vehicle charging infrastructure across the region. Bath and North East Somerset Council has subsequently been allocated £1.63m of this funding to deliver charging infrastructure within its administrative area.
To enable delivery of the programme, an Inter-Authority Agreement (IAA) has been developed to formalise the role of Bath and North East Somerset Council as Highway Authority in the implementation of the LEVI project. This report seeks approval for the Council to enter into this Agreement and authorisation for its formal execution.

Decision

The Cabinet Member agrees to delegate approval to the Executive

Director of Sustainable Communities to sign the Inter-Authority

Agreement for the Local Electric Vehicle Infrastructure Project on

behalf of Bath and North East Somerset Council.

Reasons for the decision

Entering into the IAA is necessary for Bath & North East Somerset

Council to participate in the regional LEVI programme and facilitate

delivery of publicly accessible charging infrastructure within the

authority area. Approval of the recommendation will provide the

governance framework required to support the concession

arrangements, enable the delivery of the WESTcharge network within

Bath & North East Somerset and secure the benefits of Government

funding and private sector investment in charging infrastructure.

Alternative options considered

Do not enter into the Inter-Authority Agreement.

Supporting Documents

COVID-19 Care Homes Study April 2024.pdf
Appdx1 - BNES COVID in Care Homes Report April 2024.pdf
E3734 - Local Electric Vehicle Infrastructure LEVI - Inter Authority Agreement report.pdf
E3734 LGA-3075666.pdf
E 3734 Local Electric Vehicle Infrastructure LEVI Inter-Authority.pdf

Details

ReferenceCall-ins0
OutcomeApproved
Decision date1 Oct 2026
Effective from9 Oct 2026
Expected date1 Oct 2026
Originally due1 Oct 2026
Lead officerJacob Ellis
Subject to call-inYes