Core Gigabit Fibre Network
July 17, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Purpose
Due to changes in the economic climate,
options are being provided to stop or proceed with this
project.
Content
RESOLVED that Cabinet
agrees the Preferred Option, to stop the project and not to proceed
with Phase 2 of installation of fibre and ducting.
Voting:
Unanimous
Portfolio Holder(s): Leader of the Council and Portfolio Holder for
Dynamic Places
Deputy Leader and Portfolio Holder for Connected Communities
Reason
(i)
Due to recent and potentially future volatility with
interest rates, changes in market conditions and increases in
construction costs there is now less certainty about the viability
of the business case.
(ii)
The project does not meet the current
administration’s criteria for PWLB borrowing.
(iii)
Derisks the ongoing project for the council and
aligns with the current Corporate Strategy, ‘working with
partners, removing barriers and empowering others’.
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Jul 2024 |