Warfield Community Hub – Main Works Award
August 19, 2026 Chief Executive (Officer) Key decision Approved View on council websiteFull council record
Decision
The purpose of this report is to seek approval to award the construction contract for the main works for the Warfield Community Hub in accordance with the procurement plan approved by the Cabinet in October 2024. A preconstruction services contract was awarded by the Council in August 2025.
Reasons for the decision
The Cabinet approved the delivery of the Warfield community hub, the strategic procurement plan and budget in October 2024. Within the strategic procurement plan the decision to award the main works contract was delegated to the Executive Director Communities in consultation with the Cabinet Member for Leisure, Culture, Public Protection and Democracy.
A preconstruction services contract was awarded by the Council in August 2025. Planning permission has now been approved for the hub and detailed design work completed. So there is now a requirement of award the main works contract which will commit part of the approved capital funding for the development of the proposed new community hub.
Alternative options considered
To delay or not award the contract for the main works - this will delay the delivery of the hub and increase the cost of delivery.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Aug 2026 |
| Effective from | 27 Aug 2026 |
| Expected date | 19 Aug 2026 |
| Originally due | 6 Aug 2026 |
| Lead officer | Kevin Gibbs |
| Subject to call-in | Yes |