Authority to procure Brent Civic Centre LED Phase 2 using a DPS Agreement
November 5, 2025 Director - Property and Assets (Other) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to procure Brent Civic Centre LED Phase 2 using the Supporting Decarbonisation Measures DPS agreement, including approving participation in the call-off procedure, confirming budgetary provision, and approving the invitation and evaluation of bids.
Full council record
Purpose
To request approval to use Procure
Public’s Supporting Decarbonisation Measures DPS to procure
Brent Civic Centre LED Phase 2.
Content
That the Director of Property and Assets:
i)
Approves Brent Council’s participation in a call-off
procedure under Dynamic Purchasing System (DPS) for Works and
Services, also known as the Supporting Decarbonisation Measures
DPS, for a call-off contract in respect of Brent Civic Centre LED
Phase 2.
ii)
Confirms there is sufficient budgetary provision for the proposed
call-off contract.
iii)
Approves inviting bids on the basis of the pre-tender
considerations.
iv)
Approves officers evaluating bids on the basis of the evaluation
criteria.
Reasons for the decision
The Council requires the provision of LED
lights. It has been determined that the most appropriate means of
providing the LED lights is through the procurement of a contract
for Brent Civic Centre LED Phase 2 by way of a mini-competition
under Dynamic Purchasing System (DPS) for Works and Services, also
known as the Supporting Decarbonisation Measures DPS.
Alternative options considered
Officers considered whether the Brent Civic
Centre LED Phase 2 could be provided by the Council itself but
concluded that it is best provided by a contractor.
Officers reviewed a range of procurement
options including conducting tender process but have concluded that
the use of the DPS Agreement is the most appropriate means of
procuring a contractor given the reduction in timescales, costs and
resources involved.
Details
| Outcome | Recommendations Approved |
| Decision date | 5 Nov 2025 |