A23 Phase 1 Active Travel Scheme - TRO
October 3, 2023 Transport & Sustainability Committee (Committee) Approved View on council websiteFull council record
Purpose
This report seeks committee approval for the
making of a Traffic Regulation Order (TRO) for the Active Travel
Funded A23 Phase 1 Walking, Cycling and Accessibility Improvement
scheme. It outlines the results of the TRO consultation as required
for alterations to the Public Highway for implementation.
Content
1)
That the Committee, having taken account of all
duly made representations and comments, agrees that TRO-26-2023 is
approved and can proceed to implementation stage for Parking Permit
Zone J changes only, with the amendments to the Parking Permit Zone
Q arrangement, as detailed at Section 4.3 and Appendix 3 being
pursued by officers under a future TRO.
2)
That the committee delegates authority to officers
to commence the A23 Active Travel Scheme Phase 1 (Phases 1a and 1b)
to the construction phase and to procure the Works Contract under
the authority of the Executive Director, subject to available
funding.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Oct 2023 |