Housing Major Capital Works Framework review of procurement options
September 20, 2023 Housing & New Homes Committee (Committee) Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to address insufficient contractor interest in major works projects over £300,000, the committee delegated authority to the Executive Director Housing, Neighbourhoods & Communities to procure a new framework agreement or use alternative procurement routes.
Full council record
Purpose
This report seeks approval for the dissolution
of the existing Housing major capital works framework arrangement
for Lot 2, works over £300,000, due to our being unable to
secure sufficient tenders from the contractors currently on the
framework. The report recommends replacement of this element of the
framework with the procurement of a compliant alternative framework
and /or formation of a suitable list of approved contractors for
each project to ensure that we receive sufficient tender bids for
assurance of value for money and cost comparison.
Content
RESOLVED:
2.1
That Committee delegates authority to the Executive Director
Housing, Neighbourhoods & Communities to procure a Framework
Agreement for major works over £300,000 and to enter into
call-off contracts for works under that Framework
Agreement.
2.2
That Committee grants delegated authority to the Executive Director
Housing, Neighbourhoods & Communities to procure and award
contracts for major works over £300,000 using other routes to
market where the use of a Framework Agreement is not available or
appropriate.