Period 7 Finance outturn report
December 16, 2024 Strategy and Resources Policy Committee (Committee) Key decision In call-in window View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...the committee noted the council's financial performance, including a General Fund overspend, savings delivery, risks, and Dedicated Schools Grant deficit, and approved revisions to the Capital Budget to re-profile General Fund and HRA budgets into future years.
Full council record
Purpose
To present the Strategy and Resources Policy
Committee with the latest financial outturn report and identify any
additional financial approvals that are required.
Content
The Committee RESOLVED:
To
note:
1. The
council’s General Fund forecast outturn revenue overspend of
£17.1 million at P7 2024/25 against the council approved
budget of £533.7 million.
2. The performance
on delivery of savings (Appendix A1, Section 3, Tables 3a and
3b).
3. The additional
weighted net risk of £6.1 million per the risks and
opportunities register (Appendix A1, Section 4, Tables 4a and
4b).
4. The
council’s outturn position of £13.7 million overspend
within the Housing Revenue Account to be transferred to the HRA
general reserve at the year end
(Appendix A1a, Section 5.3).
5. The
council’s outturn position of a £31.9 million overspend
(net £15.3m) in the Dedicated Schools Grant and that this
brings the carry forward deficit to £90.5 million. Following
the application of the DfE’s 24/25 Safety Valve combined with
contribution from the General Fund, a total £52.4 million is
forecast to be carried forward at the year
end in the DSG deficit reserve (Appendix A1, Section
5.4).
6. The breakeven
position on Public Health services (Appendix A1, Section 5.5).
7. The breakeven
position on the Bristol Harbour Fund (Appendix A1, Section
5.6).
8. The
council’s forecast underspend of £26.0 million against
the Capital Programme revised budget 2024/25, comprised of
£19.0 million underspend on the General Fund (including
£8.2 million underspend on corporate contingency and funds)
and £7.0million underspend on the HRA (Appendix A1, Section
6).
To
approve (6 members voting in favour and 3 against):
- Revisions to the revised Capital Budget to incorporate
the reprofiling of up to £19.0 million General Fund and
£7.0 million HRA budget into future years following the
forecast underspend at Period 7.
Related Meeting
Strategy and Resources Policy Committee - Monday, 16th December, 2024 2.00 pm on December 16, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved (subject to call-in) |
| Decision date | 16 Dec 2024 |