Harbour Walkway

February 6, 2025 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website
Full council record
Purpose

To seek approval for additional funding to
cover the costs of a partial bank collapse and increased delivery
costs, reprofile the delivery timescale and consider wider
contractor costs.

Content

That the Committee for Transport and Connectivity:

1.    Approved the pausing or
stopping of charging delay damages to KB and refund those levied to
date (without prejudice).

2.    Accepted
new funding from CRSTS over-programming (£3.5m) and EDF
(£2.7m).

3.    Approved
increasing the budget of the Harbour Walkway project from
£3.5m to £6.2m, plus the existing £3.5m – a
total of £9.7m.

4.    Approved
the use of up to £3.5m of the existing project budget to
negotiate an agreement with KB.

5.    Authorised the Executive Director
Growth and Regeneration in consultation with the Committee Chair
for Transport and Connectivity to extend/ vary the contract as
necessary to enact recommendations 1 and 4.

6.    Authorised the Executive Director for
Growth and Regeneration to invoke any subsequent extensions/
variations specifically defined in the contract(s) being awarded,
up to the maximum budget envelope outlined in this report as per
recommendation 4.

 

Supporting Documents

250124 Harbour Walkway budget amendment v8.pdf
Appendix B - Equality Impact Assessment - Harbour Walkway v3 SIGNED.pdf
Appendix C - Environmental Impact Assessment - Harbour Walkway.pdf

Details

OutcomeRecommendations Approved
Decision date6 Feb 2025
Subject to call-inYes