A4 Portway Strategic Corridor Full Business Case

February 6, 2025 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

... to approve the submission of a Full Business Case to the West of England Mayoral Combined Authority for funding to deliver the A4 Portway Strategic Corridor project and, if approved, to accept and spend the funding.

Full council record
Purpose

To seek approval for the
submission of a Full Business Case (FBC) to the West of England
Combined Authority (WECA) for City Regional Sustainable Transport
Settlement (CRSTS) funding and subject to approval, to accept and
spend the funding to deliver the A4 Portway Strategic Corridor.
 

Content

That the Policy Committee for Transport and
Connectivity

1.   Noted the approvals granted on Item 10 at the
Cabinet Meeting on 05 March 2024.

2.   Approved the submission of a Full Business
Case (Appendices E) to the West of England Mayoral Combined
Authority (WECA).

3.   Authorised the Executive Director of Growth
and Regeneration in consultation with the Director of Finance and
the Committee Chair for Transport and Connectivity, subject to
approval of the Full Business Case by WECA to: -
(I) Take all steps required to accept and spend the
City Region Sustainable Transport Settlement (CRSTS) funding amount
as set out in this report and appendices,
(ii) Tender and procure contracts (including any over
£500K) necessary to deliver the works,
(iii) Award contracts and spend the funding to
deliver the works as set out in the Full Business Case up to the
maximum budget envelope outlined in this report.
(iv) Accept, tender, award and spend on contracts to
deliver re-surfacing should further CRSTS funding become available
which may be over the key decision threshold.

Supporting Documents

Appendix D - PR_002-P0004 - A4 Portway Strategic Corridor RAID log V.5.2.pdf
Appendix H3 - FBC Appendix C - Existing bus services along the portway.pdf
Appendix H8 - FBC Appendix L - A4 Portway SC Minimum requirements_v4.pdf
A4 Portway Strategic Corridor - rpt FINAL v1.1.pdf
Appendix A - Scheme proposals consultation maps.pdf
Appendix B - Equality_Impact_Assessment_A4Portway_Strat_Corridor_v6_AHSigned.pdf
Appendix C - Environmental Impact Assessment - A4 Portway Strategic Corridor - Signed.pdf
Appendix H1 - FBC Appendix A - OAR.pdf
Appendix H - A4 Portway FBC V3.1_for issue - redacted.pdf
Appendix H2b - FBC Appendix B - Design Areas Merged-compressed 1 - Copy.pdf
Appendix H2a - FBC Appendix B - Design Areas Merged-compressed 1.pdf
Appendix H5 - FBC Appendix I - A4 Portway - CLoS LTN 1_20.pdf
Appendix H6 - FBC Appendix J - Alignment to National Regional and Local Policy.pdf
Appendix H7 - FBC Appendix K - Design Review Panel Report.pdf
Appendix H4 - FBC Appendix D - Problems_Issues_Opportunities_Statement_Arcadis Update_Aug 22.pdf
Appendix H9 - FBC Appendix O - Economic Appraisal Report v0.2.pdf
Appendix H10 - FBC Appendix P - A4 Portway Modelling Summary v2.1 ISSUED.pdf
Appendix H11 - FBC Appendix Q - Costplan_DA.pdf
Appendix H13 - FBC Appendix T - Appraisal Summary Table.pdf
Appendix H12 - FBC Appendix R - Costplan_DA 1-6_051224.Resurfacing Only.pdf

Details

OutcomeRecommendations Approved
Decision date6 Feb 2025
Subject to call-inYes