Expenditure required to support tenants of Barton House with accommodation and to complete remedial works so they can return to Barton House

January 12, 2024 Executive Director: Growth and Regeneration (Officer) Key decision Awaiting outcome View on council website
Full council record
Purpose

This decision relates to additional spend over
and above the £2.6m covered in the OED approved on 23rd
November 2023.
Further survey information has now been received which supports a
programme of works which will enable residents to return safely to
Barton House. The programme of works is scheduled to complete by 23
February 2024. The existing contract with the Holiday Inn runs
until the end of January and therefore needs to be extended.
Contractually this needs to be carried out before the next Cabinet
meeting and so an Urgent Key Officer Executive Decision is
needed.
This decision will enable the Council to continue to support
residents in alternative temporary accommodation until the works
above have been completed and the block is safe for residents to
return.
The decision is to spend on the above items up to a total of
£2.7m

Content

Authorise:
a)the Executive Director, Growth and Regeneration to agree a
contract extension with the Holiday Inn in respect of accommodation
to be provided and any other contracts required to support and
progress the situation.
b)spend of up to £2.7m in addition to the £2.6m
authorised in previous OED for Barton House evacuation giving a
total spend of £5.3m Officer Executive Decision published 24
November 2023Mayor's Executive Scheme of Delegation
(bristol.gov.uk)
for which there is no budgetary provision in relation to the
emergency evacuation of Barton House and the elements of spend set
out above.
To note:
c)that reprioritisation of HRA budgets will be required to
accommodate the spend.

Alternative options considered

Option 1 – not proceed with emergency
spend – would not allow the Council to continue to support
residents in alternative temporary accommodation or complete the
necessary works to make the block safe.
Option 2 – reduced spend – the essential works have
been scheduled to minimise the time and cost of alternative
temporary accommodation.

Details

OutcomeFor Determination
Decision date12 Jan 2024