Temple Island Enabling Works (common infrastructure works). 2.
November 23, 2023 Director: Economy of Place (Other) Approved View on council websiteFull council record
Purpose
The Strategic Partner offer continuity on this
project, with the various technical and professional skills
(project management and civil engineering design) to prepare the
design and planning application pack for the ‘CIWs’.
Tasks include: scheme design; update to RIBA 3 utilities package;
further investigation surveys on site; submission of planning
application; detailed design RIBA 4 in preparation for procurement
of the works.
Content
Approval to appoint the Strategic Partner to
undertake the design and submit planning application for the Common
Infrastructure Works on the Temple Island.
Details
| Outcome | Recommendations Approved |
| Decision date | 23 Nov 2023 |