Bristol Heat Pump Ready Project

October 5, 2023 Director: Economy of Place (Other) Approved View on council website
Full council record
Purpose

To enable the delivery of the project in
accordance with the Cabinet Decision of 7 February 2023
‘Bristol Heat Pump Ready Project. To take all steps required
to enter into contract with BEIS to accept and spend the funding of
up to £3.3m (including procuring and awarding contracts over
£500k) to implement the project as set out in proposals to
BEIS and to make any amendments to the project as necessary for
successful delivery.

Content

To enter into contract with Veritherm
(procured previously through the route of ‘compliant
exception’) to deliver up to 270 heat pump readiness home
surveys as part of the Heat Pump Ready Project funded by the
Department of Energy Security and Net Zero.

Details

OutcomeRecommendations Approved
Decision date5 Oct 2023