A37/A4018 Stockwood to Henbury Strategic Corridor: Workpackage 3 College Green, Park Street, The Triangle and Queens Road

March 20, 2025 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website
Full council record
Purpose

To seek approval for the submission of a Full
Business Case (FBC) to the West of England Combined Authority
(WECA) for City Regional Sustainable Transport Settlement (CRSTS)
funding and subject to approval, to accept and spend the funding to
deliver the A37/A4018 Workpackage 3 improvements.
 
To accept and spend an increased level of
funding to deliver the A4018 corridor improvement project.

Content

That the Policy
Committee for Transport and Connectivity:
1.
    Approved the submission of
a Full Business Case to the West of England Mayoral Combined
Authority (MCA)

 
2.
    Authorised the Executive
Director of Growth and Regeneration in consultation with the Chair
of the Transport & Connectivity Committee and Section 151
officer, subject to approval of the Full Business Case by the MCA
to:
a.
Take all steps required to accept and invest the City Region
Sustainable Transport Settlement (CRSTS) funding amount as set out
in this report and appendices,
b.
Procure all contracts (goods, services and works and including any
over £500K) necessary to deliver the Workpackage 3,
c.
Extend the value of the existing Highways and Associated Works
framework if there is insufficient spend remaining to cover
Workpackage 3 which may be procured before its expiry on 30th
September 2025,
d.
Award contracts and invest the funding to deliver the works as set
out in the Full Business Case up to the maximum budget envelope
outlined in this report.

 
3.
Approved an increase in the budget envelope for the A4018 Corridor
Improvements Project from £4.38m to £6.05m.
 

Supporting Documents

Appendix N - QCRA.pdf
E24019-C109-A Queens Rd-Triangle-Park St GA 9 of 19.pdf
E24019-C103-A Queens Rd-Triangle-Park St GA 3 of 19.pdf
E24019-C107-A Queens Rd-Triangle-Park St GA 7 of 19.pdf
Committee Report Template - College Green et al Final.pdf
E24019-C105-A Queens Rd-Triangle-Park St GA 5 of 19.pdf
00_Appendix A2 Updated Plans Booklet.pdf
E24019-C115-A Queens Rd-Triangle-Park St GA 15 of 19.pdf
Appendix A3 Parking Removal.pdf
E24019-C116-A Queens Rd-Triangle-Park St GA 16 of 19.pdf
E24019-C117-A Queens Rd-Triangle-Park St GA 17 of 19.pdf
Appendix E.2 - Whiteladies Road.pdf
E24019-C118-A Queens Rd-Triangle-Park St GA 18 of 19.pdf
Appendix A4 EBR.pdf
Appendix B EQIA.pdf
Appendix C EIA.pdf
Appendix A1 FBC Draft 2.0.pdf
Appendix A7 A37 A4018 Early Engagement Report - Sept 2020.pdf
Appendix A8 Public Consultation Report 080722.pdf
Appendix K - EQIA.pdf
Appendix E.1 - Park Row.pdf
Appendix G - Stakeholder Summary.pdf
Appendix M - AST.pdf
Appendix O - Modelling Technical Note.pdf
Appendix P - Schedule.pdf
E24019-C114-A Queens Rd-Triangle-Park St GA 14 of 19.pdf
Appendix T - 2022 Consultation.pdf
Appendix U - ATE Route Check.pdf
Appendix V - ATE Route Check.pdf
Appendix W - Screening proforma.pdf
Appendix R - Comms Plan.pdf
Appendix S - RAID Log.pdf
E24019-C101-A Queens Rd-Triangle-Park St GA 1 of 19.pdf
E24019-C102-A Queens Rd-Triangle-Park St GA 2 of 19.pdf
E24019-C104-A Queens Rd-Triangle-Park St GA 4 of 19.pdf
E24019-C106-A Queens Rd-Triangle-Park St GA 6 of 19.pdf
E24019-C108-A Queens Rd-Triangle-Park St GA 8 of 19.pdf
E24019-C110-A Queens Rd-Triangle-Park St GA 10 of 19.pdf
E24019-C111-A Queens Rd-Triangle-Park St GA 11 of 19.pdf
E24019-C112-A Queens Rd-Triangle-Park St GA 12 of 19.pdf
E24019-C113-A Queens Rd-Triangle-Park St GA 13 of 19.pdf
E24019-C119-A Queens Rd-Triangle-Park St GA 19 of 19.pdf
Appendix E.3 - Canons Road.pdf

Details

OutcomeRecommendations Approved
Decision date20 Mar 2025
Subject to call-inYes