Temple Island Enabling Works project extension of the Strategic Partnership support during 2025.

May 8, 2025 Executive Director: Growth and Regeneration (Officer) Approved View on council website
Full council record
Purpose

The completion of the Temple Island Enabling
Works has been delayed from May 2025 to July 2025. Additionally,
Bristol City Council (BCC) is now delivering the Common
Infrastructure Works (CIW) which is likely to further delay
completion of the construction works until October/ November
2025.
The project manager has requested the continuation of Strategic
Partner (SP) support for the extension of the works, and the
additional support required to support delivery of the CIW which
will include increased commercial, HandS and utilities support
whilst these works are being mobilised and on site. The project
requires the SP to continue supporting the project until December
2025 to allow for close-out once the contractor has demobilised
from site.

Content

Decision required to allow the project to
spend £444,903.25 + VAT of project budget on Strategic
Partner fees.
This commission will be captured as a Variation Order (number 25)
under the Strategic Partnership framework.

Details

OutcomeRecommendations Approved
Decision date8 May 2025