Managing Our Debt Project Funding to develop a Full Business Case

September 18, 2025 Executive Director: Resources (Officer) Approved View on council website
Full council record
Purpose

To approve the Outline Business Case for the
‘Managing Our Debt’ Project and approve the funding
request for project funding of £403k plus £46k
contingency to realise the target benefits and develop the Full
Business Case.

Content

Approve the Outline Business Case (including
scope and key project milestones) and approve the funding request
for additional £403k plus £46k contingency to be funded
from the Transformation Reserve to develop the Full Business
Case.

Alternative options considered

The alternative to approving the Outline
Business Case and funding to develop the Full Business Case was to
cease the Managing Our Debt Project and accept non-delivery of the
target benefits.

Details

OutcomeRecommendations Approved
Decision date18 Sep 2025