Confirmation of the use of £113k of Section 106 funding to contribute to the construction of Harbour Walkway

February 12, 2026 Director: Economy of Place (Other) Approved View on council website
Full council record
Purpose

A Section 106 contribution of
£113,102.55 was drawn down for use in the Harbour Walkway
project in January 2025. Approval is now sought to spend this
funding on the ongoing construction work.

Content

Approval for the drawn down of
£113,102.55 Section 106 funding to be spent on the Harbour
Walkway.

Alternative options considered

The Section 106 contribution was provided
specifically for the Harbour Walkway and cannot be spent on
anything else. The only other option would be not to spend it and
lead to a pressure on the Harbour Walkway budget.

Details

OutcomeRecommendations Approved
Decision date12 Feb 2026