South Bristol Liveable Neighbourhoods Project – Funding for business case

July 1, 2024 Executive Director: Growth and Regeneration (Officer) Approved View on council website
Full council record
Purpose

On 23 January 2024, Cabinet approved decision
to accept £600k in CRSTS funding from WECA.
Original commission under the Bristol City Council-Strategic
Partnership Initiative with contract value of circa £72k for
Phase 1 (feasibility study) of the SBLN Project was completed in
March 2024.
The decision is to approve additional funding for development of
the draft Full Business Case and preliminary designs by April
2025.

Content

Approval of expenditure of £273,049.70
for Phase 2 Stage 1 of the South Bristol Liveable Neighbourhoods
project to enable development of the draft Full Business Case and
preliminary designs via the Bristol City Council-Strategic
Partnership Initiative.

Details

OutcomeRecommendations Approved
Decision date1 Jul 2024