Property Transformation Programme Update – September 2024

September 16, 2024 Strategy and Resources Policy Committee (Committee) Approved View on council website
Full council record
Purpose

To provide an update on the Property
Programme.

Content

The Committee RESOLVED:
1. To note that
the report states that the PropertyProgramme’s financial
objectives include £1.248m of recurring revenue savings,
£749k of one-offsavings, and £21.6m of capital receipts
in 2024/25.
 
2. To note that
the report states that as per baselining at CLB on 14 May 2024, the
Property Programme budget is £4.781m (plus £517k
contingency held by CLB).
 
3. To note that
the report states that as per baselining at CLB on 14 May 2024, no
funding has been approved for 2025/26. The budget request for
2025/26 is subject to change and will be requested via CLB.
 
 

Supporting Documents

8 Property Programme - Sept 2024.pdf

Details

OutcomeRecommendations Approved
Decision date16 Sep 2024