East Bristol Liveable Neighbourhoods, Trial scheme installation
September 3, 2024 Executive Director: Growth and Regeneration (Officer) Approved View on council websiteFull council record
Purpose
Following a tender process via the
Council’s Highways Framework, the first phase of the East
Bristol Liveable Neighbourhood scheme is due to be installed during
the autumn of 2024.
This officer decision notice is in relation to awarding the
contract to the successful contractor, ETM ltd with a bid of
£473,862.64.
A previous delegated decision on 4 April 2023 authorised the
Executive Director for Growth and Regeneration, in consultation
with the Committee Chair and the S151 officer to take all steps
required to procure and award all necessary contracts up to the
value of £1.371m (including any individual contracts over
£0.500m) to deliver the scheme, which this 473k sits
under
Content
To approve the tender report to commence the
construction of the trial East Bristol Liveable Neighbourhood
project.
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Sep 2024 |