CRSTS Strategic Corridors (A4018/A37 Southern Section) Scheme Proposals
October 24, 2024 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council websiteFull council record
Purpose
To seek approval
to submit the Full Business Case (FBC) for CRSTS Strategic
Corridors (A4018/A37 Southern Section) to West of England Combined
Authority and subject to approval take all steps required to accept
and spend the funding and tender and procure contracts as necessary
to deliver the works.
Content
That the Committee for
Transport & Connectivity:
Approved the
submission of a Full Business Case (Appendix A and exempt appendix
E) to the West of England Combined Authority (WECA)
2.
Authorised the Executive Director of Growth and
Regeneration in consultation with the Committee Chair for Transport
and Section 151 officer, subject to approval of the Full Business
Case (at Appendix A) by WECA, to;
i.
Take all steps required to accept and spend the City
Region Sustainable Transport Settlement (CRSTS) funding amount as
set out in this report and appendices,
ii.
Tender and procure contracts (including any over
£500K) necessary to deliver the works,
iii.
Award contracts and spend the funding to deliver the
works as set out in the Full Business Case up
£6.1m
iv.
Exempt appendix E (commercially sensitive data
within the FBC)
Related Meeting
Transport & Connectivity Policy Committee - Thursday, 24th October, 2024 5.00 pm on October 24, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 24 Oct 2024 |
| Subject to call-in | Yes |