CRSTS Strategic Corridors (A4018/A37 Southern Section) Scheme Proposals

October 24, 2024 Transport & Connectivity Policy Committee (Committee) Key decision Approved View on council website
Full council record
Purpose

To seek approval
to submit the Full Business Case (FBC) for CRSTS Strategic
Corridors (A4018/A37 Southern Section) to West of England Combined
Authority and subject to approval take all steps required to accept
and spend the funding and tender and procure contracts as necessary
to deliver the works.

Content

That the Committee for
Transport & Connectivity:
 

Approved the
submission of a Full Business Case (Appendix A and exempt appendix
E) to the West of England Combined Authority (WECA)

2.     
Authorised the Executive Director of Growth and
Regeneration in consultation with the Committee Chair for Transport
and Section 151 officer, subject to approval of the Full Business
Case (at Appendix A) by WECA, to;
i.       
Take all steps required to accept and spend the City
Region Sustainable Transport Settlement (CRSTS) funding amount as
set out in this report and appendices,
ii.      
Tender and procure contracts (including any over
£500K) necessary to deliver the works,
iii.    
Award contracts and spend the funding to deliver the
works as set out in the Full Business Case up
£6.1m
iv.    
Exempt appendix E (commercially sensitive data
within the FBC)
 

Supporting Documents

Appendix D Risk Register A4018-A37 South - reformatte.pdf
Table 1.1 Appendix A1.pdf
Table 1.2 Appendix A4.pdf
Cllr Rippington - Amendment - item 8 - TC PC - 24 Oct 24.pdf
Figure 1.1 Appendix A2.pdf
Appendix A A37 A4018 South FBC - V3.0 Redacted.pdf
Figure 1.2 Appendix A3.pdf
Figure 1.3 Appendix A5.pdf
Appendix B Equality Impact Assessment - A37 South.pdf
Appendix C Environmental Impact Assessment - A4018-A37 Strategic Corridors South V2.pdf
Committee Report Final Final.pdf

Details

OutcomeRecommendations Approved
Decision date24 Oct 2024
Subject to call-inYes