Pavilion Quarter, Aylesbury - Phase 1 Walkway and Temporary Car Park (Decision to be taken)
January 10, 2025 Leader, Deputy Leader and Cabinet Member for Planning (Cabinet member) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to release £895k of capital budget for the accelerated delivery of a new permanent walkway and temporary car park into phase 1 of the Pavilion Quarter Project in Aylesbury, and to delegate authority for procurement and contract agreements to the Service Director for Commercial Property & Regeneration.
Full council record
Purpose
A change request to release funding for the delivery of the pedestrian walkway and temporary car park
Decision
Recommendations:
To agree the change request to release capital budget of £895k for the accelerated delivery of the new permanent walkway and temporary car parking, into phase 1 of the Pavilion Quarter Project in Aylesbury (former Gala Bingo Hall).
To provide delegated authority to the Service Director for Commercial Property & Regeneration in consultation with the Deputy Cabinet Member for Town Centre Regeneration for the following:
To undertake a procurement exercise for a contractor and to subsequently enter a construction contract to advance the installation of the new permanent walkway and temporary car park works with the preferred contractor and to enter into any necessary agreements with adjoining landowners to facilitate the delivery of these works.
Details
| Decision date | 10 Jan 2025 |
| Effective from | 17 Jan 2025 |
| Subject to call-in | Yes |