Aylesbury New Primary Grid Connection - Revised Delivery Contract and Capacity Allocation

January 4, 2024 Leader (Other) Key decision Awaiting outcome View on council website
Full council record
Purpose

An update on the way forward for the Aylesbury
Grid Reinforcement Project.

Content

The
Leader:
 

·        
AGREED that the Council will enter into a revised
contract with UK Power Networks (UKPN) for the delivery of the AGR
Project, noting that significant changes to the regulatory
environment have removed the market failure which originally
required intervention by the Council.

·        
APPROVED the use of HIF-funded capital budget of
£3,203,170 within the Capital Programme to progress the
Council contractual delivery requirements.

·        
AGREED to delegate authority to the Corporate
Director, Planning, Growth & Sustainability, to sign the
contract variation.

Details

Decision date4 Jan 2024
Subject to call-inYes