Finance Monitoring Report August 2024

October 7, 2024 Executive (Other) Key decision Approved View on council website
Full council record
Purpose

To provide a monthly budget monitoring report
to Executive

Content

Resolved
 

(1)           
That the council’s financial management report as at the end
of August 2024 be noted.
 

(2)           
That the use of reservse requests, set
out at Appendix 5 to the report, be approved.
 

(3)           
That the reprofiling of capital projects beyond 2024/25 (set out at
Appendix 1 to the report) and the subsequent update to the
programme budget for this financial year be approved.
 

(4)           
That the reprofiling of £0.393m from future years budget into
the 2024/25 capital project for Castle Quay (cost centre 40144) be
approved.
 

(5)           
That the use of £0.133m from the Digital Futures Programme
capital budget (Cost Centre 40326) to progress work on the Robotic
Process Automation Pilot be noted.
 

(6)           
That the forecast overspend be noted and Council be recommended to
agree an increase in the capital budget for CDC Office Relocation
to Castle Quay project by £0.646m.
 

Related Meeting

Executive - Monday 7 October 2024 6.30 pm on October 7, 2024

Supporting Documents

Executive Finance Performance Report August 2024-25.pdf
Appendix 2 - Detailed Revenue Narrative on Forecast August 2024.pdf
Appendix 3 - Virements and Aged Debt August 2024.pdf
Appendix 4 - Funding August 2024.pdf
Appendix 5 - Use of Reserves and Grant funding August 2024.pdf
Addendum to Finance Monitoring Report August 2024.pdf
Appendix 1 - Capital August 2024.pdf

Details

OutcomeRecommendations Approved
Decision date7 Oct 2024
Subject to call-inYes