Selsey Coastal Scheme - Proposed Accelerated Works
December 2, 2025 Cabinet (Cabinet collective) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to mitigate the risk of coastal defence failure at West Beach, they approved submitting a funding application to the Environment Agency for accelerated coastal defence works and delegated authority for contractor appointments and expenditure, contingent on securing full funding.
Full council record
Purpose
1.1 This report seeks approval to submit an
application to the Environment Agency for Grant in Aid (GiA)
funding to deliver accelerated coastal defence works at West Beach,
where existing defences are deteriorating. The proposed works aim
to reduce the risk of defence failure in advance of the Selsey
Coastal Scheme.
Content
RESOLVED
That
Cabinet:
1.
Approves the submission of an application to the
Environment Agency for Grant in Aid funding to deliver accelerated
works to the West Beach frontage, via a Business Case Update
Report.
2.
Approves the procurement and appointment of a
contractor and subsequent construction of the accelerated works,
subject to the securing of full Grant in Aid funding (paras. 4.3
and 4.4).
3.
Approves that delegated authority be granted to
the Director of Planning and Environment, in consultation with the
Chief Operating Officer and Director of Corporate Services: to
appoint contractors to agree project financial tolerances and to
authorise expenditure of the Grant in Aid funding.
4.
Notes the current funding uncertainties at this
stage (Para. 4.4 and 7.3).
Related Meeting
Cabinet - Tuesday 2 December 2025 9.30 am on December 2, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 2 Dec 2025 |
| Subject to call-in | Yes |