All Seasons Leisure Centre Improvements - Early Works Packaage
October 13, 2025 Executive Member (Early Intervention) (Cabinet member) Key decision Approved View on council websiteFull council record
Content
Recommendations
approved.
Reasons for recommendations
1.
To ensure that the project meets the timescales
specified in the Salix funding agreement. Adhering to these
deadlines is crucial for securing the allocated funding under the
Public Sector Decarbonisation Scheme 4 (PSDS4), enabling the
decarbonisation works at All Seasons Leisure Centre to proceed
without delay.
2.
Aligns with Chorley Council's commitment to its
green agenda by actively reducing the council’s carbon
footprint. The implementation of these early decarbonisation works
at All Seasons Leisure Centre demonstrates a tangible step towards
environmental sustainability and supports efforts to meet local and
national climate objectives.
Other
options considered and rejected
Proceeding with the works as
part of the wider scheme was not pursued due to the risk of failing
to meet the Salix funding expenditure deadlines.
Details
| Outcome | Recommendations Approved |
| Decision date | 13 Oct 2025 |
| Subject to call-in | Yes |