Purpose
Decision by the Leader of the Council to approve the award of the construction contract following completion of the Early Contractor Involvement (ECI) procurement process, as set out in report PES/523 to Cabinet on 24 June 2026.
Decision
Approve the award of the construction contract for the Three Bridges Station Improvement Scheme to Bidder 1.
This decision was taken in consultation with the Cabinet Member for Planning & Economic Development, Head of Law & Governance and Head of Corporate Finance.
Details
| Reference | 0 |
| Outcome | Recommendations Approved |
| Decision date | 11 Nov 2026 |
| Effective from | 16 Nov 2026 |
| Lead officer | Lynn Hainge |
| Subject to call-in | Yes |