County Hall Options Appraisal - Outline Business Case for the Future of CCHQ
January 11, 2024 Cabinet (Cabinet collective) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the recommendations outlined in the County Hall Options Appraisal - Outline Business Case for the Future of CCHQ.
Full council record
Purpose
County Hall Options Appraisal - Outline Business Case for the Future of CCHQ
Decision
RESOLVED to:
1)
Receive and note
the findings of the Outline Business Case for the future of County Hall;
2)
Approve the
recommended option, in which the Council moves to a smaller new headquarters on
the Matlock Campus site and that the main County Hall campus is redeveloped to
deliver a mixed use;
3)
Approve taking
the recommended Option 3 forward to the more detailed business case stage and
due diligence;
4)
Support the
inclusion of £0.375m in the Capital Programme for 2024/25 to fund the
development of the full detailed business case and request approval for the
funding of this next stage of work in the sum of £0.375m, subject to approval
of the 2024/25 Capital Programme by Full Council in February 2024; and
5)
Approve the
delegation to the Director of Property in consultation with the Director of
Legal and Democratic Services the power to procure and appoint such consultants
as may be required for due diligence and development of the Option 3 detailed
business case including where appropriate the extension or variation of
existing contracts within the funding envelope of £0.375m (Subject to this
amount being approved by Full Council in February 2024 as part of the 2024/25
Capital programme).
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Jan 2024 |
| Subject to call-in | Yes |