ICT Strategy Update

January 28, 2025 Strategy and Resources Committee (Committee) Awaiting outcome View on council website
Full council record

Decision

Following consideration, the Committee unanimously resolved to:

(1)       Note the changes to the ICT strategy outlined in appendix 1 to the report.

(2)       Agree up to £45,000 of funding from the Corporate Projects Reserve to provide the refresh of the corporate website.

(3)       Note the progress that has been made so far on the ICT roadmap, allowing for the understandable delays that came about as a result of personnel changes in ICT leadership.

(4)       Note that whilst the agreed budget for the ICT Programme of work is still largely on track that there are inflationary and other external pressures that are resulting in cost increases.

Supporting Documents

ICT Strategy Update Appendix 2.pdf
ICT Strategy Update Appendix 3.pdf
ICT Strategy Update.pdf
ICT Strategy Update Appendix 1.pdf

Details

OutcomeFor Determination
Decision date28 Jan 2025