Replacement CCTV System at Hudson Leisure Centre

September 3, 2026 Head of Leisure Services (Officer) Key decision Approved View on council website
Full council record

Purpose

To place an order with Chubb Fire Safety, following a procurement process, for replacement of the CCTV system at Hudson Leisure Centre.

Following a conditions survey of all aged assets at site, it was found that the CCTV system had reached the end of its workable life cycle and will need replacement. This is both a safety and maintenance concern as not having eyes across your building could make it.

Decision

An order to the value of £54,110 will be placed with Chubb Fire Safety following a procurement process, following a procurement process, for replacement of the CCTV system at Hudson Leisure Centre.

Reasons for the decision

•    Existing equipment is reaching the end of its useful life and is critical for the functioning of the centres.

•    A procurement exercise has been conducted following FDC’s procurement policy and Chubb Fire Safety have quoted in line with the Procurement framework illustrating value for money.

•    FDC has a budget for condition survey works within the capital programme.  As replacement of a whole capital asset, FDC is bound by the contract with Freedom to carry out this replacement.

Alternative options considered

None – this is critical equipment.

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date3 Sep 2026
Effective from12 Sep 2026
Subject to call-inYes