May 29, 2026 Executive Director of Children's Services (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Executive Director of Children's Services approved recommendations on 29/05/2026. The decision approved payment of a licence fee to Pause for Change for two years (£42,000 maximum) and commissioning of a Pause Programme delivery contract for 23 months (£386,000 maximum) via the Consultancy+ Framework. The Nelson Trust was awarded the delivery contract.
Full council record
Purpose
Pursuant to an Authorisation from: Council’s Scheme of Delegation GEN 1: To enter into any contract for works and the supply of goods and services
Decision
In line with the Gloucestershire Children’s Services Ambitions Plan (2024) and in consultation with the Cabinet Member for Children’s Safeguarding and Care:
DECISION
- To approve the payment of a licence fee to Pause for Change for a period of two years (maximum value £42,000). This licence is required to enable delivery of the nationally accredited Pause model.
- To approve the commissioning of a Pause Programme delivery contract (23 months, including mobilisation and delivery) at a maximum value of £386,000, and to agree the use of the Consultancy+ (C+) Framework as the route to market.
These are two separate but interdependent arrangements: the licence enables the use of the Pause model, while the contract secures a provider to deliver the programme.