Digital Infrastructure, Inclusion & Innovation Strategy - Delivery and Investment Plan

October 21, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Gloucestershire Council's Cabinet decided on 21/10/2026 to approve the Digital Infrastructure, Inclusion & Innovation Strategy's delivery programme and budget commitments for 2026/27 and 2027/28. Authority was delegated to the Director of Economy and Planning to implement the plan, including refining delivery arrangements and conducting a procurement process for a countywide Digital Inclusion Service.

Full council record

Purpose

On the 28 January 2026 Cabinet adopted the Digital Infrastructure, Inclusion & Innovation Strategy. This Cabinet report outlines the delivery programme of the strategy and seeks approval for the proposed investment allocation across the strategy themes.

Decision

Cllr Julian Tooke presented the delivery programme for the Digital Infrastructure, Inclusion and Innovation Strategy and sought approval for the proposed investment allocation across the strategy themes.

Having considered all of the information, Cabinet noted the report and

RESOLVED to:

a) Note the DIIIS intended four-year delivery programme 2026/27 to 2029/30 outlined in Appendix A.

b) Approve budget commitments for 2026/27 and 2027/28 outlined in Appendix A of the report and note that any further expenditure beyond this date will be subject to future approval through the Council’s governance processes. The exception to this is the awarding of the Digital Inclusion Service Tender which, once awarded in 2026/27, will cover the lifetime of the Digital Strategy until 2030.

c) Delegate authority to the Director of Economy and Planning, in consultation with the Cabinet Member for Business, Economic Development, Planning and Infrastructure, to implement the approved DIIIS delivery and investment plan. This is limited to funding allocations within the approved DIIIS budget and project details. This covers:

•  Refining delivery arrangements.

•  Conducting a competitive procurement process in respect of a three-year contract for the provision of a countywide Digital Inclusion Service. The award of any future contract will be subject to compliance with the Procurement Act 2023, GCC Contract Procedure Rules and approval processes applicable at the time. The procurement route, contract value, market approach and evaluation methodology have been or will be confirmed during project initiation and procurement planning.

•  Awarding such contract to the preferred tenderer following completion of the procurement process.

Related Meeting

Cabinet - Wednesday 21 October 2026 10.00 am on October 21, 2026

Supporting Documents

For Cabinet - DIIIS_Delivery and Investment Plan Cabinet Report October 26.08 - Copy.pdf
For Cabinet - EQIA - Digital Infrastructure Inclusion Innovation Strategy 26 - Copy.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date21 Oct 2026
Effective from29 Oct 2026
Expected date21 Oct 2026
Originally due21 Oct 2026
Subject to call-inYes