Maurer, Metcalfe, Holly & New Becquerel Courts, Faraday, Alamaro, DaVinci & Newton Lodges, Greenwich Millenium Village Phases 1 & 2, West Parkside, Greenwich, SE10 0BY - Ref: 24/3879/F

April 8, 2025 Planning Board (Committee) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to grant full planning permission for the removal and replacement of combustible external cladding materials on buildings within Greenwich Millennium Village Phases 1 & 2, subject to specific conditions regarding materials, resident consultation, and minor wording changes.

Full council record
Content

Resolved that full planning
permission be granted for the removal and replacement of
combustible materials and build-ups in the existing external
cladding materials on buildings within the original phases 1 &
2 of Greenwich Millennium Village (Maurer Court, Metcalfe Court,
Faraday Lodge, Alamaro Lodge, Da Vinci Lodge, Newton Lodge, Holly
Court & New Becquerel Court).
 
Subject to –

·     
The Conditions set out in Appendix 2 of the report
and its addendum.

·     
Amendment to Condition 7 – Materials, that the
Sto Render Grain: Strukturmuster 1.0 / be colour matched to the
original vibrant colour pallet on the Faraday, Alamaro & Newton
blocks (in Phase 2); so as to maintain the original architectural
design ideal of these iconic blocks.

·     
The following additional Informative:
Informative 2
‘In
respect of the Greenwich Millenium Village blocks Faraday Lodge,
Alamaro Lodge & Maurer Court only, the applicant and the
management company are advised to engage in discussions with
residents to conduct an investigation into the feasibility of the
cladding product Parklex Prodema GRCLAD-B as a potential
alternative replacement material for the existing Cedar Wood
cladding as suggested by residents.’  
 
That the Assistant Director
(Planning & Building Control) be authorised to make any minor
changes to the detailed wording of the recommended conditions as
set out in Appendix 2 of the report, its addendum and the minutes
of this Planning Board meeting, where the Assistant Director
(Planning & Building Control) considers it appropriate, before
issuing the final decision notice.

Related Meeting

Planning Board - Tuesday, 8th April, 2025 6.30 pm on April 8, 2025

Supporting Documents

Appendicies to Greenwich Millenium Village Phases 1 2 West Parkside Greenwich. Ref 24-3879-F.pdf
Item 6 - Addendum to Greenwich Millenium Village Phases 1 2 . Ref 24-3879-F.pdf
Greenwich Millenium Village Phases 1 2 West Parkside Greenwich. Ref 24-3879-F.pdf

Details

OutcomeRecommendations Approved
Decision date8 Apr 2025