Charlton Riverside Opportunity Area Regeneration: Scheme and Estimate Report

October 29, 2026 Leader of the Council (Cabinet member) Key decision In call-in window View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Leader of the Council approved a Scheme and Estimate budget of £822,332 and delegated authority to the Director of Place and Growth to enter into a Phase 1 Landowners Collaboration Agreement with London Homebuilding Partnership LLP. The decision was made on 29/10/2026. The Leader also approved the preparation of a detailed Meanwhile Use Strategy for Charlton Riverside.

Full council record

Purpose

To approve the Scheme and Estimate Report to allow for the progression of place-making, partnership working and recruitment in relation to the Charlton Riverside regeneration project.

Decision

  1. Approved a Scheme and Estimate budget at a value of £822,332 to facilitate the regeneration of Charlton Riverside as set out in the report.
  2. Approved the Outline Commercial Terms as set out in Appendix F of this report and delegate authority to the Director of Place and Growth to enter into a Phase 1 Landowners Collaboration Agreement with London Homebuilding Partnership LLP ("Hyde") to facilitate the regeneration of part of Charlton Riverside.
  3. Approved the preparation of a detailed Meanwhile Use Strategy for Charlton Riverside to facilitate place-making and activate Council land and buildings for social, cultural and commercial purposes.
  4. Noted a further formal governance report will be presented to agree next steps beyond Stage 1 of the Collaboration Agreement and to implement the Meanwhile Use Strategy.
  5. Agreed to treat the information contained in the confidential Appendices A, C, D, E, F and G to this report as exempt from the provisions of paragraph 3 of Schedule 12A to the Local Government Act 1972 (as amended) (Information relating to the financial or business affairs of any particular person including the authority holding that information) and agreed that this exempt information contained in the confidential Appendices shall not be released to the press or public.

Supporting Documents

Charlton Riverside Opportunity Area Regeneration.pdf
Appendix B Charlton Riverside Delivery Framework.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved (subject to call-in)
Decision date29 Oct 2026
Expected date29 Oct 2026
Originally due16 Oct 2026
Lead officerEmma Sweeney
Subject to call-inYes