1A & 1C Eynsham Drive, Abbey Wood, London, SE2 9RQ
October 8, 2024 Planning Board (Committee) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to grant full planning permission, subject to referral to the Mayor of London, completion of a Section 106 Legal Agreement, and specified conditions, for the demolition of the existing car wash and pet hospital at 1A & 1C Eynsham Drive and redevelopment of the site into a mixed-use development including a re-provided pet hospital, co-living accommodation, hotel accommodation, parking, landscaping, playspace, and refuse facilities.
Full council record
Purpose
24/0146/F
Content
Resolved that full planning
permission be granted for the demolition of existing car wash and pet hospital and any
associated structures and the re-development of the site for a
mixed-use development, including buildings, comprising a
re-provided pet hospital (E(e)) floorspace, co-living accommodation
(sui generis), hotel accommodation (C1 use), car parking spaces,
cycle parking, hard and soft landscaping measures including
playspace provision and refuse and recycling facilities.
That consent is subject
to:
(i)
Referral of the application to the Mayor of London
as required under the terms of the Town and Country Planning (Mayor
of London) Order 2008.
(ii)
The satisfactory completion of a Section 106 (S106)
Legal Agreement (obligations set out in Section 32), as set out in
the report and its addendum.
(iii)
The Conditions set out in Appendix 2 and its
addendum.
That the Assistant Director
(Planning & Building Control) be authorised to:
(i)
Make any minor changes to the detailed wording of
the recommended conditions as set out in the report (Appendix 2),
its addendums and the minutes of this Planning Board meeting, where
the Assistant Director (Planning & Building Control) considers
it appropriate, before issuing the final decision
notice.
(ii)
Finalise the detailed terms of the section 106
agreement (including appended documents) and form of the planning
obligations as set out in this report (Section 32), its addendums
and the minutes of this Planning Board meeting.
(iii)
Consider, in the event that the Section 106
Agreement is not completed within three (3) months of the date of
this Planning Board resolution, whether consent should be refused
on the grounds that the agreement has not been completed within the
appropriate timescale, and that the proposals are unacceptable in
the absence of the recommended planning obligations; and if the
Assistant Director (Planning & Building Control) considers it
appropriate, to determine the application with reasons for refusal
which will include the following:
·
In the absence of a legal agreement to secure the
necessary obligations regarding affordable housing, transport and
highway works, cycling infrastructure, public realm improvements,
employment and training and sustainability the development would
fail to mitigate its impact on local services, amenities and
infrastructure, environmental sustainability and open space
contrary to policies H1, H4, H5, SI 2, SI 3, T2, T4, T9 and DF1 of
the London Plan (2021) and H3, EA(c), E1, CH(a), IM1, IM4, IM(a),
IM(b) and IM(c) of the Royal Greenwich Local Plan: Core Strategy
with Detailed Policies (Adopted July 2014), and the Planning
Obligations (s106) Guidance SPD (July 2015).
Related Meeting
Planning Board - Tuesday, 8th October, 2024 6.30 pm on October 8, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 8 Oct 2024 |