Weyside Urban Village – Phase 02 Onsite Infrastructure (Sludge Lagoon)
November 28, 2023 Joint Strategic Director - Place (Officer) Key decision Approved View on council websiteFull council record
Content
Approval to enter into a contract with Main
Contractor.
The Works are key to the WUV programme and will:
? Provide Enabling Works and Infrastructure to Service Development
Plots in Phase 2, including the enabling and builders work for the
UKPN Primary Substation.
? Expend infrastructure Grant monies from the HIF within the
current extended Grant expenditure window (to end March
2025).
The works can be summarised as follows:
• Design and installation of infrastructure to site and
developer plots –
• site clearance,
• Ground remediation works,
• New drainage infrastructure,
• Formation of primary roads, and
• Installation of services infrastructure and tails.
Details
| Outcome | Recommendations Approved |
| Decision date | 28 Nov 2023 |
| Subject to call-in | Yes |