Riverside SANG Bridge replacement

February 25, 2026 Parks and Countryside Development Lead (Other) Approved View on council website
Full council record
Content

To issue a contract to Morton Pattison Ltd to
install a new vehicle bridge to access Riverside Nature Reserve
SANG

Reasons for the decision

To replace existing access bridge that needs
replacing due to rotting timber and consequently insufficient load
bearing capacity for the vehicles that need to use it.
Suitable bridge access is required for operational site management,
including planned boardwalk replacement works, and fire service
access to wildfire risk area.
The bridge is also part of the approved SANG (Suitable Alternative
Natural Green Space) circular walk and national cycle
network.

Alternative options considered

To replace the bridge with a pedestrian access
only bridge. This would, however, prevent adequate operational and
fire service access to the site. Resulting in additional site
management cost from arranging temporary access and use of
alternative management methods.

Details

OutcomeRecommendations Approved
Decision date25 Feb 2026