WUV Off-site Highways NEC Supervisor
September 3, 2024 Joint Assistant Director: Regeneration and Economic Development (Officer) Key decision Approved View on council websiteFull council record
Content
GBC utilised the Pagabo Framework Lot 4 for
Site Supervisor/Clerk of Works to procure a suitable NEC Supervisor
to act for GBC on the Off-site Highways NEC Contract initially,
with the Council being able to utilise Ross Quality for the next
four years for NEC Supervisor services. The top ranked consultant
was selected as appropriate and fulfilling the criteria for the
project. The project and procurement team met with the consultant
to discuss the project and the capability of the consultant.
Ross Quality provided a fee proposal which was vetted by the
project team, and a best and final offer submitted. This has been
deemed to provide an adequate level of resource to cover the
several junctions over a staggered programme for a duration of
approximately two years. A contingency is to be applied on top of
the proposed fee to account for any variations through the life of
the project.
Reasons for the decision
To enter into contract for NEC Supervisor
services for Off-site Highways
Alternative options considered
None
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Sep 2024 |