NORTH ANGLESEY SITES AND PREMISES PROJECT - BUSINESS JUSTIFICATION CASE+
October 3, 2025 North Wales CJC Economic Well-being Sub-committee (Committee) Awaiting outcome View on council websiteFull council record
Content
DECISION
1. To approve the Business Justification Case (BJC+) for the North Anglesey
Sites and Premises project, subject to Welsh Government and UK Government
approval of the assurance process undertaken.
2. To delegate to the Portfolio Director in consultation with the Chair,
Vice-chair, Section 151 Officer and Monitoring Officer to confirm the final
costs and benefits post procurement are in line with the approved business case
and enter into a funding agreement with Isle of Anglesey County Council (IoACC) for the delivery of the project, subject to Isle of
Anglesey County Council addressing the outstanding issues set out in section 7
of the report and securing all necessary internal approval for the project.
3. That the approval from the Sub-committee is valid for a period of six
months and should the project not proceed to a signed funding agreement during
this time, it will be required to return and re-present the business case to
the Sub-committee for approval.
Related Meeting
North Wales CJC Economic Well-being Sub-committee - Friday, 3rd October, 2025 9.30 am on October 3, 2025
Details
| Decision date | 3 Oct 2025 |