HCE S629 Kings Hall Leisure Centre Refurbishment Project Financial Business Case Update

November 24, 2025 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to enable the Kings Hall Leisure Centre Refurbishment project to proceed, the Cabinet approved an increase of £19.478m to the capital costs, bringing the total to £90.92m, and noted the associated funding streams and revenue impact.

Full council record
Purpose

Financial Business Case update and Design and
Build Contracts Award Report

Content

RESOLVED:

3.1 
Approve capital costs for the Kings Hall Leisure Centre
Refurbishment
 
project of up to £90.92m, an increase of £19.478m from
Cabinet’s
 
approval on 30 September 2024, and note the funding streams
and
 
revenue impact associated with this.

Related Meeting

Cabinet - Monday 24 November 2025 6.00 pm on November 24, 2025

Supporting Documents

20251114 HCE S629 Kings Hall Leisure Centre Refurbishment Project Financial Business Case Update.pdf

Details

OutcomeRecommendations Approved
Decision date24 Nov 2025