Project Appraisal: Reading Road South Pedestrian Crossings
October 30, 2025 Director of Universal Services (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...the Director approved the Project Appraisal for Reading Road South Pedestrian Crossings, authorizing the procurement, expenditure, and contractual arrangements necessary to implement the scheme at an estimated cost of £330,000, fully funded by developer contributions, while also directing the progression of necessary orders, notices, and agreements.
Full council record
Content
1. That the Director of Universal Services
approves the Project Appraisal for Reading Road South Pedestrian
Crossings, as outlined in the supporting report.
2. That the Director of Universal Services gives approval to
procure, spend and enter into necessary contractual arrangements,
in consultation with the Head
of Legal Services, to implement this scheme, at a total estimated
cost of £330,000, to be fully funded from developer
contributions.
3. That the Director of Universal Services and the Head of Legal
Services progress orders, notices, statutory procedures and secure
and enter into all appropriate agreements, licences, consents,
permissions, rights or
easements necessary to enable implementation of the
scheme.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 30 Oct 2025 |