1. That the Director of Universal Services
approves the Project Appraisal for Popley Accessibility
Improvements (Basingstoke) - Sherborne Road Pedestrian Crossing
scheme, as outlined in the supporting report.
2. That the Director of Universal Services gives approval to
procure, spend and enter into necessary contractual arrangements,
in consultation with the Head of Legal Services, to implement this
scheme, at a total estimated cost of £488,000, to be funded
from Section 106 Developer Contributions.
3. That the Director of Universal Services and the Head of Legal
Services progress orders, notices, statutory procedures and secure
and enter into all appropriate agreements, licences, consents,
permissions, rights or easements necessary to enable implementation
of the scheme.