1. That the Director of Universal Services
approves the Project Appraisal for the Manydown Cycle Route Initial
Works, as set out in this report.
2. That the Director of Universal Services gives approval to
procure, spend and enter into necessary contractual arrangements to
implement this scheme, at a total estimated cost of £279,000,
to be funded from Customer and Communities Improvement Fund and
Active Travel Fund grants.
3. That the Director of Universal Services and Legal Services
progress, enter into, and secure all appropriate licences, deeds of
dedication, agreements, consents, rights, permissions and easements
necessary to enable the works to be undertaken on land owned by
third parties.